Greens Reconstruction and Fairway Work – late 2016

Published on 25th October 2016 in Guest Only

Prior to making a green fee or stay and play booking, guests should be aware that reconstruction of the 2nd and 5th greens commenced in early September. The works include:

  • Replacing the subsurface profile and surrounds
  • Enlarging the left side of the 5th green and slightly softening the general slope of the green
  • Re-laying the existing turf of the two greens
  • Replacing the green surrounds turf
  • Reconstructing greenside bunkers of the 2nd and 5th
  • Reconstructing the approach bunker on the 5th
  • Constructing new fairway bunker left side of the 5th fairway

During the reconstruction works, a temporary 2nd green will be in play approximately 40 metres short of the 2nd green and a temporary 5th green will be 78m metres short of the 5th green and played as a par 4. The two new greens will return to play late October. Work is also underway on the 12th and 14th fairway bunkers.